The City of Harrisonville’s asphalt project on South Independence Street will begin Monday morning and continue through Oct. 28, closing the street to through traffic.
Crews will begin milling out the old asphalt on Monday beginning on South Street, to the west of Sanders Street and working east towards Independence Street. Milling will continue Tuesday moving north on Independence Street towards Mechanic Street, stopping at the intersection and then continuing to Wall Street. Paving will take place Monday through Wednesday.
The roads will be closed to through traffic on Independence from Mechanic Street to South Street and South Street from Independence to just west of Sanders Street.
North Independence Street from Mechanic Street to Wall Street and Marler Lane will also be closed during paving.
Flaggers will be in place in some areas and all work is weather permitting.